Public Notices / Road Construction 

  1. Tue, Aug 14 - Fri, Nov 30

  2. Mon, Oct 8 - Tue, Oct 23

  3. Mon, Oct 8 - Tue, Oct 23

  4. Mon, Oct 22 - Fri, Oct 26

View All

Current Road Construction Projects

Multi-Layer Polymer Overlay Project

Two structures located at Green-Randolph Road over South Otter Creek (D.6-9.0) and Fancy Creek Road over Fancy Creek (E.2-5.6). Contract awarded to PCiRoads LLC in the amount of $92,059.55. Precon meeting to be held Sept. 21. Contractor anticipated starting October 8, 2018. Project will be rescheduled for the spring of 2019 due to weather conditions.

Denison Avenue & Marlatt Avenue Roadway Reconstruction Project

Located on Denison Avenue north from the Manhattan Fire Department Headquarters Station to the intersection of Marlatt Avenue and on Marlatt Avenue from College Avenue east to the intersection of Tuttle Creek Boulevard. Bid awarded to Bayer Construction Co. Inc.  Project begins on March 1, 2018, and is estimated to be complete in approximately 165 days, weather permitting. 

Marlatt Avenue from Tuttle Creek Blvd. west to College Avenue is open to traffic. Please note, this will continue to be an active WORK ZONE with a 30 MPH  Speed Limit.

Various construction operations will occur along the roadway
during the next few weeks. PLEASE DRIVE WITH CAUTION.

Traffic Control was switched to open Marlatt Ave. to restricted traffic. The center crown lane of Denison Ave was completed except for the south taper (next phase). Approximately 33% of the northbound lane of Denison Ave is complete. 

When completed, Denison Avenue will be a three lane concrete curb and gutter roadway.  Marlatt Avenue from Denison Avenue to Tuttle Creek Boulevard will be a four lane concrete curb and gutter roadway. Additional turn lanes will be added on Marlatt Avenue at both the Denison Avenue and Tuttle Creek Boulevard intersections.  At this time, there are no immediate plans to install traffic signals at the Denison Avenue / Marlatt Avenue intersection.

Future Construction Projects

Anderson Avenue Bridge Replacement 

  • Consultant - BG Consultants 
  • Consultant currently designing a shoo-fly detour on Chicago Ave.
  • Field Check completed - May 23, 2018
  • Borings on Anderson Ave. at the Keats bridge have been completed - Aug. 3, 2018
  • Anticipate Office Check plans in Mid-September

Fancy Creek Road Bridge Replacement

  • Consultant - Bartlett & West, Inc.
  • Staff reviewed Field Check Plans
  • Field Check completed - June 20, 2018
  • Office Check Plans have been reviewed by staff.
  • Awaiting Final Plans - August 20, 2018

Kitten Creek Road Culvert Replacement

  • Consultant - Olsson Associates
  • No action taken - August 20, 2018

Peach Grove Road Culvert Replacement

  • Consultant - SMH Consultants, P.A.
  • Field Check completed - May 10, 2018
  • Awaiting Office Check Plans - August 20, 2018

Stockdale Park Road Bridge Replacement

  • Consultant - Schwab Eaton, P.A.
  • Field Check completed - May 11, 2018
  • Awaiting Office Check Plans - August 20, 2018

Vinton School Road Bridge Replacement

  • Consultant - Alfred Benesch & Co.
  • Field Check completed - June 25, 2018
  • Office Check Plans received, under review by staff - August 17, 2018